Bremerton Capital Group Office Building
Bremerton, Washington | Renovation
Project Specifications:
Originally built in 1965 using concrete panels over clad with baseball size granite stones embedded in cement, this project was in trouble. The stones were coming loose and falling off the facade, putting pedestrians below at risk. The Owner's choice was to over clad the building with metal panels, which proved to be too expensive. Instead using EIFS and a light gauge steel grid system, was the perfect solution. The renovation, a framing masterpiece, was completed without interruption of the occupied building. The use of colors makes the improved project stand out, and its new appearance is both bold and handsome. It was the most dramatic transformation ever completed in its firm’s history, according to the EIFS applicator.
Manufacturer: Dryvit Systems, Inc.
Contractor: Applied Restoration, Inc.
Distributor: Salmon Bay/Commencement Bay
Owner/Developer: Bremerton Capital Group
Architect: Rice Fergus Miller