Long Beach Memorial Pediatric Medical Office Building
Long Beach, CA | Healthcare
Project Specifications:
The design team’s flexibility and curiosity about prefabrication made this project a great opportunity for EIFS. Panelizing the exterior cut the project skin schedule by 3 months and resulted in a 19-day dry in rather than the expected 120-day duration. Seven unique bright colors were used on the façade, which is very eye-catching. The juxtaposition of the shapes combined with the contrasting colors make this project a testament to the strength of EIFS.
Manufacturer: Sto Corp.
Contractor: Nevell Group, Inc.
Distributor: FBM
Owner/Developer: Long Beach Medical Center
General Contractor: Turner Construction
Architect: C-A Architects